Un article trouvé pour ce sujet.
|
|
|
|
|
|
|
|
A linear programming problem |
2013-02-27 |
|
Kelley pose la question : A manufacturer of skis produces two types: downhill and cross-country. Use the following table to determine how many of each kind of ski should be produced to achieve a maximum profit. What is the maximum profit? What would the maximum profit be if the time available for manufacturing is increased to 48 hours.
|
Downhill |
Cross-country |
time available |
manufacturing time per ski |
2 hrs |
1 hr |
40 hr |
finishing time per ski |
1 hr |
1 hr |
32 hr |
profit per ski |
$70 |
$50 |
|
Penny Nom lui répond. |
|
|
|