Un article trouvé pour ce sujet.
|
|
|
|
|
|
|
|
Fill behind a retaining wall |
2009-02-05 |
|
Fausto pose la question : i'm trying to figure out how many cubic yards i will need. I built a retaining wall that it's 5 feet high, running 90 feet long. There is a slope running to the wall of 24 degrees. The distance from the top of the slope to the wall is 12 feet. I don't know how to calculate how many cubic yards of fill dirt i need in there. Please help. Thanks! Harley Weston lui répond. |
|
|
|